Almost a bridge to nowhere
Construction, architectural issues on skywalk, security project have added $7.8 MILLION; if span opens in November, it will be more than a year BEHIND SCHEDULE
Steve Marcus
Work continues on the pedestrian walkway connecting McCarran International Airport’s B and C gates. A companion project — a security checkpoint annex with 12 lanes — is likely to open next month.
Monday, Aug. 18, 2008 | 2 a.m.
Beyond the Sun
The long-delayed skywalk connecting the B and C concourses at McCarran International Airport is no longer a bridge to nowhere, but the public still won’t be able to use it until late November at the earliest.
The pedestrian bridge was supposed to have been completed more than 10 months ago, along with a two-level security annex aimed at shortening checkpoint lines. The good news is the 12 new security lanes are scheduled to open next month.
Passengers of Southwest Airlines, the busiest carrier at the airport, will make the most use of the new C gates security annex, but the benefits should be felt by everyone flying out of the D gates as well because now they share a security checkpoint area with C gate passengers.
But the skybridge and security annex project is going to cost millions more than its initial price tag — and a battle between the contractor and the county seems likely.
The initial price of construction was $65.4 million, according to early 2006 county documents, but the cost today is pegged at $72 million. (Airport officials say that two years ago, they anticipated the cost might rise as much as 10 percent.)
But that’s just construction cost. The architectural costs went up too.
Airport executives blame “fairly significant” design flaws and a glacial construction process. Redesigns have meant architectural costs of the bridge have risen to $2.86 million, 72 percent more than the original budget of $1.66 million. But the architect, Domingo Cambeiro, says the contractor, Flagship Construction, is at fault for many of the delays and cost increases.
One problem was that the end of the bridge was 9 inches higher than its second-floor entrance to the existing B concourse, which is home to US Airways and some overflow Southwest Airlines flights.
The skyway roof had a design error too, says Randall Walker, the airport’s director of aviation. It “was sloped in both directions, so it had to be redesigned,” he says.
Flagship’s construction pace is what really irks Walker, though.
“The bridge is languishing,” he says. “What distressed me ... is that I walked (the bridge) at 3:30 p.m. on a weekday in July. And there was absolutely no one doing work out there.”
With the project behind schedule, Walker says he had expected Flagship to work diligently, perhaps add extra shifts, to get the project finished. It’s what the contractor handling the expansion of the D concourse did.
Now, Walker anticipates that when construction on the annex-bridge project wraps up, the airport and Flagship will enter legal negotiations over costs and delays.
“There will be an interesting closeout” to the project, he says. “We’re significantly at odds.”
The airport and the contractor appear to have squabbled from the beginning over the timeline. Flagship initially had difficulty securing a bond, prompting a 120-day delay, Cambeiro says. The project should have begun Feb. 20, 2006. Flagship, Walker says, sought an excused delay, which he rejected.
A Flagship official, briefly apprised of Walker’s overall remarks, offered this single statement: “The entire facts are not being portrayed accurately.”
•••
Walker acknowledges he isn’t fond of the bridge concept on principle. The airport’s priority, he explains, is to serve passengers for whom Las Vegas is a destination, not passengers who simply fly through without ever leaving the airport. But, he said, he determined the skywalk is necessary to ease mounting demand at McCarran.
Officials at carriers including Southwest Airlines and US Airways encouraged the construction of the bridge. The airlines have paid for a daily shuttle to run between the two concourses, but will discontinue the service upon the bridge’s opening, Walker says.
The idea of a bridge was conceived before the 9/11 attacks as a link between the B and C concourses, to and from the existing buildings, to prevent additional traffic on typically lengthy security lines. With a connection between concourses, passengers on layovers in one concourse wouldn’t have to pass through the security checkpoints.
The proposal was revisited in spring 2004. But before the county hired a contractor in mid-2004, airport officials scrapped that $15 million plan for a bridge alone and decided a project larger in scope, one that would address several aspects of an airport bursting at the seams, was called for. Cambeiro had begun designing the original bridge when the county called it off in favor of the larger project.
After changing yet another plan, the airport decided to group the bridge project with construction of a security annex, one with 12 lanes.
Later, with construction on the skyway and annex lagging, the airport instructed Flagship to make the annex the priority, Walker says. The annex is more critical today because the airport is opening an expanded D concourse next month. Without the 12 additional lanes, there would be even more of a crush at the existing C/D security wing.
But because multiple projects were revised and consolidated, different architects were employed. Cambeiro attended to the bridge.
“It does sound like we duplicated things,” county Commissioner Chris Giunchigliani says.
Cambeiro and his project manager, Mark Dowell, attribute the flaws in Flagship’s work on the bridge to old drawings of the existing B concourse that included errors and changes made during construction by project manager Bechtel. And communications issues between the parties further slowed the process, Cambeiro says.
The elevation of the B concourse’s second floor couldn’t be identified, he says, because his company was unable to survey it. “We couldn’t expose the floor because the concourse was in operation,” he adds.
The second floor of the two-story pedestrian bridge ultimately was sloped to accommodate the difference in elevations, Walker says.
As for the roof, Dowell alleges that Flagship “did not install the edge of the roof the way it was intended, so it created problems with the slope.” A redesign was needed.
Walker says he would welcome Cambeiro’s company back to the airport. The architect has assisted on several projects at the airport over the years, building good will. And in Walker’s view, anyone can make an error — “it’s how you deal with them that’s the issue.”
That explains much of his frustration with Flagship. But despite his preference that the county not use the company again at the airport, he doubts it will be disqualified from future projects.
Discussion: 5 comments so far…
Post a comment
- Most Read
- Discussed
- Most E-mailed
- Police: 3 arrested in officer’s death have gang ties
- Las Vegas condo hotels remain a tough sell — just ask Trump
- LV companies in denial about problem gambling
- Corrections officer with Metro killed in U.S. 95 crash
- System fails to catch contractor’s family tie with county
- Where to watch UFC 106
- UNLV and Southern Illinois will be guarded tonight
- Fontainebleau contractors say sales process is flawed
- SEC sues former gaming exec for alleged insider trading
- Station Casinos, lenders agree to rent decrease at 4 properties
Blogs
The Kats Report
For props, Lewis Black needs only his manic delivery and torrid material (3 Comments)
Elsewhere
Sands China raises $2.5 billion in Hong Kong IPO (1 Comment)
Marquardt v. Sonnen scheduled for UFC 109
Bloggity, Bloggity, Bloggity
Will a fourth consecutive title by Jimmie Johnson be good or bad for NASCAR? (3 Comments)
Top Chef: Las Vegas
The Jet Stream: And then there were four
Top Chef Episode 12: On keeping it simple
Miech Again
Chilly start for Chace, but Stanback says he'll warm up (2 Comments)
- Live chat
- Tuesday, noon PST
- Chat with Krista Creelman
- Problem Gambling Center executive director Krista Creelman will answer questions about gambling addiction from Las Vegas Sun readers from noon to 1 p.m. Tuesday, Nov. ... Submit question
Calendar »
- 22 Sun
- 23 Mon
- 24 Tue
- 25 Wed
- 26 Thu
-
UFC 106 at Mandalay Bay Events Center
Mandalay Bay Events Center | 7 p.m. to 11 p.m.
-
Julio Iglesias at the Las Vegas Hilton
Las Vegas Hilton
-
Natasha Wicks hosts at Hawaiian Tropic Zone
Hawaiian Tropic Zone | 10 p.m. to 11:59 p.m.
-
Tito Ortiz hosts at Tao
Tao | 10 p.m. to 11:59 p.m.
-
Hiroshima at Santa Fe Station
Santa Fe Station
-
Frank Mir hosts at LAX
LAX Nightclub | 10 p.m. to 11:59 p.m.
-
The Four Tops at The Orleans Showroom
Orleans Hotel-Casino
-
Amir Sadollah hosts at Prive
Prive | 10 p.m. to 11:59 p.m.
The Sun
Locally owned and independent for more than 50 years.
Technorati











So nice to spend 72million while flights and passengers are on the decline like never before. Just one more thing to pass on the residents that haven't left
Sounds like a re-occuring theme.......
Government officals sign a contract to build a new building for $xxx.
Cost overruns nearly double the cost.
Fingers point everywhere.
Sounds like a lot of cash flowing under the table to me.
Tony would be proud!!!!
These stupid smelly airport cost overruns are passed on to airlines. They pass it on to the passengers. The result is higher tickets cost. Therefore fewer tourist come. The final result is lost jobs in Nevada.
Bechtel is the project manager. The same company that has ballooned the reconstruction of Iraq by 200% and more.
I have no problem with the expansion, as it will be needed in the near future. I remember the late 70's when many residents cried that 'McCarren 2000' plans were excessive, they ended up not being enough. Or Woodbury's plans for the 215 beltway, when that was approved many thought 'what a waste', now it seems 215 is behind.
Future vision is needed in governement, those that can't see past today cost us MUCH more in the long run.
Bechtel The same giant Company that has destroyed The Nevada Test Site