City Hall work behind schedule
Tuesday, July 23, 2002 | 10:41 a.m.
The Las Vegas City Hall building addition is running five months behind schedule because of a sloping floor that needs to be repaired, a city spokesman said.
However, officials still hope to bring the $20.2 million expansion, which includes a cantilever and adjacent parking garage in under budget, despite $800,000 in additional costs, including repairs to a seven-inch slope over a 50-yard width of floor.
The projected costs included a $1 million contingency, which means that while the cost of the 40,000-square-foot structure has gone over original projections, the project technically is $200,000 under budget.
The building addition originally was scheduled to open in April, but now is projected to open in September, city officials said.
It is customary for such projects to be completed before the city and contractors sit down to haggle over who is responsible for costs of repairs.
archive
- Most Read
- Discussed
- Most E-mailed
- CityCenter’s Mandarin Oriental makes Vegas debut
- As national jobless rate improves, LV sees signs of trouble
- Pacquiao-Mayweather fight on, March date likely
- Sub-freezing temperatures hit Las Vegas
- Court upholds sex conviction for Las Vegas magician
- UNLV president denies reports of Livengood as new AD
- Barrick Gold to work on mine despite court ruling
- Downsizing shifts passengers to smaller airlines
- From Eva Longoria Parker to a cluster of execs, crowd takes a shine to Crystals
- Rebels try to avoid the ‘trap’ at Santa Clara
Blogs
Elsewhere
Dawn Gibbons' story: Nevada's first lady talks about her divorce, humiliation and fears
The Kats Report
Kirk Kerkorian: CityCenter is 'simply the most amazing' Vegas project ever (1 Comment)
Robin Leach's Las Vegas Celebrity Watch
Great Santa Run: Unofficial 14,595 runners would be a new record
Elsewhere
Rampage Jackson to return to UFC (3 Comments)
Politics: Ralston's Flash
Superintendents want state to immediately seek Race to Top funds
Top Chef: Las Vegas
The Jet Stream: The great Jennifer debate (2 Comments)
The Kats Report
From Eva Longoria Parker to a cluster of execs, crowd takes a shine to Crystals (4 Comments)
Calendar »
- 6 Sun
- 7 Mon
- 8 Tue
- 9 Wed
- 10 Thu
-
Chickenfoot at The Joint
The Joint | 8 p.m. to 11:59 p.m.
-
The Ultimate Fighter 10 Finale at the Pearl
The Pearl at the Palms | 4 p.m. to 10 p.m.
-
Great Santa Run at Town Square
Town Square | 8 a.m. to 10 a.m.
-
Willie Nelson at Planet Hollywood Theatre for the Performing Arts
Planet Hollywood Resort and Casino | 9 p.m. to 11:59 p.m.
-
Cash'd Out at Aliante Station
Aliante Station Casino and Hotel | 9 p.m. to 11:59 p.m.
-
Brooks & Dunn at the Hilton
Las Vegas Hilton
-
Ron White performs at the Mirage
Terry Fator Theatre
The Sun
Locally owned and independent for more than 50 years.
Technorati